Demonstrating CCS Feasibility with a Waste-to-Energy Plant in Switzerland

Status: Complete (2021)

Project Overview 

With carbon capture and storage (CCS) found to be the most promising solution for the decarbonization of waste-to-energy plants in an earlier study, this project set out to investigate the feasibility of the complete CCS chain (capture, transport and storage) for the waste incineration plant KVA Linth in Switzerland. The study was conducted by KVA Linth and the Sustainability in Business Lab at ETH Zürich and funded by Innosuisse and the Association of Operators of Swiss Waste Incineration plants (VBSA). 

​

  • An amine-based post-combustion CO2 capture unit to capture 100,000 tons of CO2 per year was designed for KVA Linth and could be operational in 24 months at CAPEX of CHF ~25 million without heat integration and CHF ~30 million with heat integration depending on plant specific configurations.

  • The Northern Lights project offshore of Norway has been identified as a viable CO2 storage site that is most advanced and open to third parties.

  • After assessing various transport options for captured CO2, a combination of a liquid-CO2 pipeline to a private SBB loading station and train to Rotterdam at a cost of CHF 78 per ton of CO2 has been identified as the most realistic option for now. At scale, transport via pipeline is the only feasible option.

  • Expected storage costs ex Rotterdam, are CHF 33-61 per ton of CO2 by 2030.

  • The costs for the first-of-a-kind full CCS-chain have been estimated at around CHF 156-190 per ton of CO2.

  • Currently, none of the potential revenue sources are sufficient and financial support from the government or regulatory changes will be necessary to make the project commercially viable. Switzerland currently lacks regulations for process emissions from CO2 capture plants.

  • The implementation of the CCS chain at KVA Linth requires the public's financial support as well as collaboration and support from a network of policy makers, regulatory bodies, the supply chain industry and other stakeholders, such as cantons, communes, and NGOs. 

  • Long-term cost reduction and scale-up of CCS also requires a CO2 pipeline network. Several stakeholder groups – including the waste-to-energy and other industries, federal and regional entities and scientific institutions – are involved in discussions around the possibility of realizing a CO2 collection and transport network.

​

Report see below!

​

Please contact Marian Krueger for more information.

Funding and Partners
Picture1.png
kva_logo.jpg
VBSA Logo.jpg
Kanton Glarus.png
Downloads
Public Project Summary
Capture 2.JPG
News and Blog Features 
Petrissa 2.JPG

sus.lab`s CCS Project gets Featured on the Swiss News

RTS - Le 19h30 - Starts at 3:28 

It is already possible to capture over 4 million tons of CO2 emitted each year by waste to energy plants in Switzerland. However, to permanently remove these emissions from the atmosphere, we need to build a CO2 transport network towards the North Sea.  Read More